Home / Products / Core Stacking & Assembly Lines / LXD-260-2 Offline Transformer Core Stacking Line
  • LXD-260-2 Offline Transformer Core Stacking Line
  • LXD-260-2 Offline Transformer Core Stacking Line
  • LXD-260-2 Offline Transformer Core Stacking Line
  • LXD-260-2 Offline Transformer Core Stacking Line
  • LXD-260-2 Offline Transformer Core Stacking Line
  • LXD-260-2 Offline Transformer Core Stacking Line
  • LXD-260-2 Offline Transformer Core Stacking Line
  • LXD-260-2 Offline Transformer Core Stacking Line
  • LXD-260-2 Offline Transformer Core Stacking Line
  • LXD-260-2 Offline Transformer Core Stacking Line
  • LXD-260-2 Offline Transformer Core Stacking Line
  • LXD-260-2 Offline Transformer Core Stacking Line
  • LXD-260-2 Offline Transformer Core Stacking Line
  • LXD-260-2 Offline Transformer Core Stacking Line
  • LXD-260-2 Offline Transformer Core Stacking Line
  • LXD-260-2 Offline Transformer Core Stacking Line
  • LXD-260-2 Offline Transformer Core Stacking Line
  • LXD-260-2 Offline Transformer Core Stacking Line

LXD-260-2 Offline Transformer Core Stacking Line

Product Definition

While automation has been widely adopted in other industries, transformer core production has long relied on traditional processes — manual sequencing and manual lamination stacking — which cause silicon steel sheet wear, deformation during handling, increased core losses, higher noise, and higher production costs. These are common problems throughout the industry.

The LXD-260-2 No-Material-Bin Column-Type Automatic Core Stacking Equipment was developed to address uncontrollable issues in manual stacking. During operation, unpunched silicon steel sheets cut by a transverse shearing line are stacked into columns in the cutting and stacking sequence, transported to the column-material mechanism of the stacking machine. An automatic moving mechanism with vacuum suction cups places the material onto the positioning track; after positioning, the moving stacking mechanism with suction cups assembles and stacks the core according to the core drawing requirements.

Contact Us
Add Cart
Applications Feedback

Buyer's Responsibilities

  • Supply and connect the power cable to the equipment electrical cabinet per public utility conditions; connect the required grounding cable to the designated connection point on the equipment.
  • Construction of equipment foundations, pipelines, embedded parts, and grounding systems.
  • Lifting equipment (crane, forklift, etc.) required for unloading, positioning, and installation/commissioning of equipment at the buyer's site.
  • Water, compressed air (including 2 m³ air receiver tank), electricity, and auxiliary materials for equipment commissioning.
  • Materials required for trial operation during commissioning.

Delivery, Acceptance & Inspection

  • Inspection standards: this Technical Agreement and the manufacturer's applicable national standards.
  • Acceptance and inspection shall be carried out by both parties at the supplier's production site in accordance with the Technical Agreement; equipment is shipped after passing inspection.
  • Full performance testing shall be conducted at the end user's site; both parties shall perform item-by-item acceptance per the Contract and Technical Agreement; an Acceptance Report shall be signed by both parties upon passing.

Equipment Composition

Complete Equipment Composition
No. Component Qty. Remarks
1 Yoke Lamination Column Pre-storage Cart 1 set
2 Yoke Lamination Column Transfer Conveyor Line 1 set
3 Yoke Lamination Grab & Lift Mechanism 1 set
4 Yoke Lamination Gripping Mechanism 1 set
5 Yoke Lamination Material Transport & Positioning Track 1 set
6 Yoke, Center Limb & Side Lamination Stacking Mechanism 1 set
7 Finished Product Stacking Elevator 1 set
8 Center Limb & Side Lamination Transport & Positioning Guide Rail 1 set
9 Center Limb & Side Lamination Gripping Mechanism 1 set
10 Center Limb & Side Lamination Grab & Lift Mechanism 1 set
11 Center Limb & Side Lamination Column Transfer Cart 1 set
12 Center Limb & Side Lamination Rotation Cart with Pre-storage 1 set
13 Finished Product Transport Line & Finished Product Clamping Positioning Platform 1 set
14 Safety Guards 1 set
15 Electrical Control Cabinet 1 set Includes system controller, servo drives, and frequency inverter

Main Technical Parameters

No. Performance Parameter LXD-260-2
1 Lamination Specifications Width 40–260 mm
Thickness 0.18–0.3 mm
Side Limb Length 450 mm (centerline length) – 1700 mm (tip-to-tip length)
Yoke Length 450 mm (centerline length) – 1700 mm (tip-to-tip length)
Center Limb 450–1440 mm (tip-to-tip length)
Max Core (L×W×H) 1700×1700×400 mm
2 Required Lamination Accuracy (supplied by buyer) S-Value (Bow) Single-sided error within total length ≤0.1 mm
Waviness Height error within total length ≤2 mm
Burr ≤0.02 mm
Width ≤±0.1 mm
Length ≤±0.2 mm
Center Limb Angle Deviation (after left/right flip) ≤0.1 mm
Length Consistency of Yoke, Side & Center Limb ≤0.1 mm
45° Angle Accuracy of Side, Yoke & Center Limb ≤±0.025°
V-Notch & 45° Angle Overlap (same yoke flipped) ≤0.1 mm
3 Stacking Accuracy Same-grade Length Direction ≤±0.5 mm (excluding supplied sheet accuracy error)
Same-grade Width Direction ≤±0.5 mm (excluding supplied sheet accuracy error)
Same-grade Thickness Error (stacked by sheet count) ≤1 mm (excluding supplied sheet thickness error)
Note: Core accuracy is simultaneously affected by sheet cutting accuracy and stacking accuracy. Manual reshaping after stacking is required to achieve higher precision. If the shutdown for reshaping due to the buyer's higher precision requirements reduces equipment productivity in normal production, responsibility lies with the buyer and is unrelated to the supplier's equipment.
5 Column Material Alignment Requirements Sheet Supply and Loading 1. Sheets are cut into columns by the transverse shearing line or manually stacked in columns according to the core drawing column structure and quantity (each grade count must be exact — excess or missing sheets will affect stacking efficiency and require manual intervention). 2. Both machine-formed and manually stacked columns must meet the column alignment requirements in this specification. 3. If the buyer's column alignment does not meet the technical parameters, or if columns contain extra, wrong, or missing sheets, causing frequent equipment stoppages affecting efficiency, the buyer is responsible for resolving the column supply issue.
Column Height ≤400 mm
5-Limb Core Column Height Consistency ≤1 mm
Same-grade Width Direction Misalignment ≤5 mm
Same-grade Length Direction Misalignment ≤5 mm
Same-grade Width Centerline Deviation on Material Slot ≤5 mm
Column-to-Plate Width Centerline Deviation ≤5 mm
Single-column Width Direction Misalignment ≤5 mm
Single-column Length Direction Misalignment ≤5 mm
Single-column 45° Bevel Side Misalignment ≤5 mm
Single-column Center Limb Tip Misalignment ≤5 mm
Single-column Position on Material Plate Length-direction center position deviation ≤20 mm; End fixed position deviation ≤20 mm
6 Stacking Cycle Time Approx. 6 s 1 stroke (5 sheets/stroke); approx. 10 strokes/min; ~100 sheets/min (2-stack type) Acceptance standard core: Width 80–140 mm; Max length 850 mm (tip-to-tip); Thickness 280 mm
7 Air Supply Pressure ≥0.6 MPa
Total Air Consumption (energy-saving vacuum generator; low consumption; reduces compressed air costs) ≤0.6 m³/min
8 Equipment Noise ≤70 dB
9 Equipment Color Factory standard: Main color: Light Grey 7035, Sky Blue 5015; Moving parts: Signal Yellow 1003. Custom colors available upon request.
10 Working Voltage Voltage Fluctuation 380 V ±10%
Frequency 50 Hz ±2%
11 Installed Capacity 90 kW

 

Main Components & Brands

No. Item Brand
1 Control System & Touch Screen Siemens
2 Servo Drive System Siemens / Inovance / Hechuan / Weichuang
3 Frequency Inverter Inovance or equivalent
4 Electrical Components Schneider low-voltage switches; Panasonic relays or equivalent
5 Push Buttons Eaton (Moeller) or equivalent
6 Solenoid Valves SMC (Japan) or equivalent
7 Cylinders & Regulating Valves SMC (Japan) or equivalent
8 Vacuum System & Suction Cups SMC (Japan) or equivalent
9 Linear Guide Rails WON (Korea) / Yintai / Jiding or equivalent
10 Ball Screws NanGongYi (ground screws) / Jinqiu or equivalent
11 Racks & Gears Atlanta (Germany) / APEX or equivalent
12 Variable-frequency Motors Siemens (Bode) / Jiegong / Yinda or equivalent

Technical Documentation

No. Document Name Quantity
1 Equipment Parts List 2 copies
2 Certificate of Conformity 1 copy
3 Electrical Schematic Diagram 2 printed copies + 1 electronic file
4 Electrical Wiring Diagram 2 printed copies + 1 electronic file
5 Electrical Component Manuals 1 copy each
6 Equipment Operation Manual (including operating procedures, maintenance & service norms) 2 printed copies + 1 electronic file
7 Installation Floor Plan 1 printed copy + 1 electronic file
8 Equipment Foundation Drawing 1 printed copy + 1 electronic file

Installation, Commissioning, Training, After-Sales Service & Warranty

Installation, Commissioning & Training The supplier's engineers will provide free on-site training on operation, maintenance, upkeep, and process guidance. Time required: Installation and commissioning are generally completed within 2 weeks. Training duration is determined by the buyer's operators' proficiency and the buyer's requirements.
After-Sales Service If equipment problems arise, the supplier dispatches personnel for repair and provides basic troubleshooting and daily maintenance guidance to the buyer's mechanical and electrical maintenance staff.
Daily Response Time Response within 24 hours. On-site arrival: same day within the supplier's province; next day for other provinces.
Holiday Response Time Response within 24 hours. On-site arrival during holidays if the buyer has on-duty personnel.
Note: 1. For faults requiring on-site service, arrival is generally within 24 hours; phone resolution is preferred where possible. 2. The supplier provides lifetime service; discounted spare parts, components, and technical support continue after the warranty period. 3. If the buyer defaults on payment after equipment acceptance, the supplier makes no warranty commitment.
Warranty Period 12 months from the date of final acceptance. During the warranty period, if a fault arises due to equipment quality issues or correct operation per the supplier's procedures, the supplier provides free parts and repair at no cost to the buyer. If a fault arises due to the buyer's failure to follow operating procedures or overloading, the supplier promptly resolves the fault and charges only the component cost.